Overbilling vs. Underbilling: What Your WIP Schedule Is Trying to Tell You

Close-up of a WIP schedule marked up in red pen, flagging overbilling vs underbilling on each job

Overbilling vs. underbilling is the gap between what you’ve billed on a job and what you’ve actually earned on it so far. Bill more than you’ve earned and the job is overbilled. Earn more than you’ve billed and it’s underbilled. Your work-in-progress (WIP) schedule works out that gap for every open job, every month, and it’s one of the few numbers that can warn you about a problem job before the year-end financials do.

The trouble is that most owners read the total. The total can look perfectly fine while two jobs underneath it are going sideways.

Construction WIP schedule marked up in red pen, showing overbilling vs underbilling by job
A September WIP schedule after review. The total says the company is $25,000 overbilled, which sounds harmless. The jobs underneath tell a different story.

How to calculate overbilling vs. underbilling

It’s the same three steps on every line of the schedule:

  • Cost to date ÷ estimated total cost = percent complete
  • Percent complete × contract value (including approved change orders) = earned revenue
  • Billed to date − earned revenue = over/(under) billing

A positive result means the job is overbilled. A negative one, shown in parentheses, means it’s underbilled.

Take Job 101 in the schedule above, a $2.4 million medical office build-out estimated to cost $1.92 million:

  • $1,152,000 spent ÷ $1,920,000 estimated = 60% complete
  • 60% × $2,400,000 contract = $1,440,000 earned
  • $1,560,000 billed − $1,440,000 earned = $120,000 overbilled

If you take one thing from the math, make it this: everything hangs on the estimated total cost. Percent complete, earned revenue, profit, and the over/under figure all come from that one forecast. When it’s stale, the whole line is wrong, and as you’ll see below, it’s usually wrong in the flattering direction.

Overbilling isn’t automatically a problem

Some overbilling is normal, and often it’s deliberate. A schedule of values that weights mobilization, site work, and early materials brings cash in before your heaviest costs hit, so the job funds itself instead of running on your line of credit.

Hand-drawn chart on engineering paper comparing billed and earned revenue over a construction job
Billing usually runs ahead early, slips behind mid-project when pay apps and change orders lag, and catches up at closeout if someone actually bills it.

It goes wrong when someone mistakes overbilled cash for profit. That money is a prepayment for work you still owe. If it’s already gone to distributions, a new truck, or an overrun on another job, you’ll feel it in the last third of the project, when billings slow down and the remaining costs don’t.

Signs your overbilling has crossed the line:

  • Your cash doesn’t comfortably cover your total overbillings. You’ve spent money you haven’t earned yet.
  • Overbillings keep climbing company-wide while margins on finished jobs keep slipping. New jobs are paying for old problems.
  • A job stays heavily overbilled late in its life. That can mean the cost estimate is too low.

If profit looks healthy and the bank balance doesn’t, our guide to managing cash flow on a construction project walks through the fixes.

Why lenders worry more about underbilling

On paper, underbilling is an asset. In practice it’s a soft one, because it rests on your own estimate of the work rather than an invoice your customer has accepted. Sureties and banks know that, which is why a pattern of underbillings draws more questions than a pattern of overbillings.

Most persistent underbilling comes from one of these:

  • Slow billing. Pay apps go out late because nobody owns the billing deadline.
  • Unsigned change orders. Crews do the extra work, nobody prices or signs the change order, and the cost lands on the job without the revenue.
  • Disputed work. An owner contests part of a pay app and that piece just sits there.
  • A back-loaded schedule of values. The early phases were priced too low to bill against what they actually cost.
  • A stale cost estimate. The job is over budget, and nobody has updated the forecast.

The first four have a fix, and it’s usually a process, not a journal entry. The last one matters most, because it hides real losses.

When “underbilled” really means “over budget”

When a job runs over budget and nobody updates its estimated total cost, the extra spending makes the job look further along than it really is. A higher percent complete means more earned revenue, and more earned revenue makes the job look both underbilled and more profitable. Both are wrong.

WIP report line corrected in red pen after a cost re-forecast turns an underbilled job into an overbilled one
Job 107 before and after the project manager’s re-forecast. Same costs, same billings, very different job.

Job 107 is a $2.4 million office build-out. In October the project manager re-forecast the remaining work and added $240,000 for framing labor and rework. Here’s what changed:

  • Percent complete: 60% before, 53% after
  • Over/(under): $120,000 underbilled before, $40,000 overbilled after
  • Gross profit to date: $288,000 before, $128,000 after
  • Projected margin: 20% before, 10% after

Same costs, same billings. The extra $160,000 of gross profit the job had been showing was never there.

That’s why accurate job costing and an honest monthly forecast of cost to complete matter more than the spreadsheet itself. And if a re-forecast shows a job will lose money overall, the accounting rules generally require you to book the entire expected loss right away rather than spreading it over the remaining work. Better to find that out in October than in the tax meeting.

Where the numbers land on the balance sheet

Each job nets to a single position, either an asset or a liability, never both. Underbilled jobs roll up into a current asset, and overbilled jobs roll up into a current liability.

Contractor balance sheet with underbillings and overbillings highlighted as contract assets and liabilities
The WIP totals carry straight onto the balance sheet: underbillings with current assets, overbillings with current liabilities.

You’ll run into two sets of names for these lines, and they mean the same thing:

  • Underbillings: “contract assets” under ASC 606, or “costs and estimated earnings in excess of billings” on older statements
  • Overbillings: “contract liabilities” under ASC 606, or “billings in excess of costs and estimated earnings” on older statements

The month-end adjusting entry depends on how your system records billings. If billings post straight to revenue, an underbilled job needs a debit to the contract asset and a credit to revenue, and an overbilled job needs the reverse. Adjust from last month’s balance rather than reposting the cumulative amount. Then make sure the two reports agree. Total earned revenue on the WIP should equal revenue on the income statement, and total over- and underbillings should match the balance sheet. If they don’t, sort that out before anyone outside the company sees either one.

Retainage is a separate matter. It’s money you’ve billed that the customer is holding back, so it belongs in receivables, not in your underbillings. Under ASC 606 your CPA may present retainage on unfinished jobs within contract assets, but it still shouldn’t get mixed into the over/under figures on your WIP.

What your surety is looking for

Your WIP schedule is one of the first documents a bonding company asks for, and underwriters read it closely. Here’s what they look for:

  • Whether your overbilling vs. underbilling position has been stable or drifting. Many will discount underbillings when they calculate your working capital.
  • Whether cash actually backs your overbillings.
  • Fade on completed jobs. Margins that consistently shrink between bid and closeout point to estimating or execution problems.
  • Whether the WIP ties to your financial statements.

None of that takes anything fancy. Clean, consistent monthly financial reporting does more for bonding capacity than most contractors realize, because it shows the underwriter you know your jobs as well as they do.

A month-end routine that keeps the WIP honest

The schedule is only as good as what goes into it. At each month-end close, run through this for every open job:

  1. Get every cost onto the job, including late invoices, payroll accruals, and field purchases.
  2. Have the project manager re-forecast cost to complete. Don’t roll last month’s number forward.
  3. Add approved change orders to the contract value, and keep pending ones on a separate list with an owner and a date.
  4. Recalculate percent complete, earned revenue, and the overbilling vs. underbilling figure for each job.
  5. Flag any job that shows an underbilling two months running.
  6. Compare total overbillings to cash on hand.
  7. Compare each job’s projected margin to last month and to the original bid.
  8. Tie the WIP to the general ledger and post the adjustment.

Once you’ve built the schedule, our four ways to analyze a WIP schedule cover what else to look for.

Overbilling vs. Underbilling FAQs

Is overbilling illegal?

No. On a WIP schedule, overbilling just means you've billed more than you've earned so far under percentage-of-completion, usually because your schedule of values front-loads early work. You still can't bill beyond what your contract and pay applications allow, but that's a separate question.

Is underbilling an asset or a liability?

An asset. It's revenue you've earned and haven't invoiced yet. Financial statements report it as a contract asset, or under the older label, costs and estimated earnings in excess of billings.

Is overbilling the same as deferred revenue?

It's the same idea applied to a construction contract. An overbilling is money you've billed for work you haven't performed yet, so it sits on the balance sheet as a liability until you earn it. Under ASC 606 it shows up as a contract liability, often alongside customer deposits.

Does retainage count as underbilling?

No. You've already billed retainage; the customer is just holding it until the job is done. Track it as retainage receivable, separate from your over and under figures.

How often should I update the WIP schedule?

Every month, as part of close. If you only prepare the WIP at year-end, you find problems months after you could have done something about them.

Do smaller contractors need a WIP schedule?

If your jobs run longer than a month, yes. Even contractors allowed to use the completed-contract method for taxes benefit from seeing which jobs are making money while there's still time to act. If you're bonded or borrowing, your surety and bank will ask for one anyway.

How should I handle unapproved change orders on the WIP?

Conservatively. Record the costs as you incur them, but leave the revenue out until the change order is approved or collection is genuinely probable. Keep pending change orders on a list with a follow-up date, since unsigned change orders are one of the most common causes of persistent underbilling.

Can a job be overbilled and still lose money?

Yes. Overbilling only tells you billing is ahead of the work. If the job's estimated cost keeps climbing, the margin can disappear while the WIP still shows an overbilling and the bank balance still looks healthy. Watch each job's projected margin month to month, not just its over/under figure.

Why doesn't my WIP schedule match my financial statements?

Usually because someone built the WIP in a spreadsheet outside the accounting system, booked costs after running it, or didn't cut off billings and costs at the same date. Total earned revenue on the WIP should match revenue on the income statement, and total over- and underbillings should match the balance sheet. Fix the source before trusting either report.

Get a second set of eyes on your WIP

A WIP schedule is the closest thing a contractor has to an early-warning system, but only if someone reads overbilling vs. underbilling job by job, every month, with an honest forecast behind each line. LLŪM’s controllers and fractional CFOs build and review WIP schedules for construction companies every month, tied to the books and ready for your surety.